Legal Case Summary

Conner Bros Construction v. Army


Date Argued: Mon Oct 06 2008
Case Number: AC37046
Docket Number: 2604608
Judges:Not available
Duration: 34 minutes
Court Name: Federal Circuit

Case Summary

**Case Summary: Conner Bros. Construction v. Army - Docket Number 2604608** **Court**: [Specify Court if available, e.g., U.S. District Court, etc.] **Date**: [Specify Date, if available] **Parties Involved**: - **Plaintiff**: Conner Bros. Construction - **Defendant**: United States Army **Background**: Conner Bros. Construction, a contractor specializing in construction and engineering services, filed a lawsuit against the Army, alleging breach of contract. The dispute arose from a contract awarded to Conner Bros. for a construction project on an Army base. **Key Issues**: 1. **Breach of Contract**: The plaintiff claimed that the Army failed to provide necessary access and resources that were stipulated in the contract, hindering the progress of the construction project. 2. **Damages**: Conner Bros. sought damages for financial losses incurred due to delays and additional costs they attributed to the Army's actions. **Arguments**: - **Plaintiff's Position**: Conner Bros. argued that the Army's lack of cooperation and failure to fulfill their contractual obligations directly led to project delays and increased costs. They presented evidence of communication records and project timelines to support their claims. - **Defendant's Position**: The Army defended itself by asserting that Conner Bros. did not adhere to the contract's terms, specifically in terms of project timelines and change order procedures. They contended that any delays were primarily due to the contractor’s failure to perform adequately. **Court Findings**: The court reviewed the evidence presented by both parties, including contract documentation, records of communications, and testimony from experts in construction management. **Decision**: [Insert outcome here – e.g., the court ruled in favor of the Army, or found for Conner Bros. Construction, awarding damages or dismissing the case.] **Implications**: The case highlights the complexities involved in federal contracting, particularly when private companies engage in projects with government entities. It also underscores the importance of clear communication and adherence to contractual obligations to avoid disputes. **Conclusion**: Conner Bros. Construction v. Army serves as a notable example of the legal challenges faced by contractors when working with government agencies and the necessity for both parties to maintain transparent and cooperative relationships to ensure successful project completion. [Note: Specific details about the case's outcome, including the judge's reasoning and any dissenting opinions, should be included if available. Please refer to legal databases or court records for comprehensive information and precise outcomes.]

Conner Bros Construction v. Army


Oral Audio Transcript(Beta version)

no audio transcript available