Legal Case Summary

Garco Construction, Inc. v. Secretary of the Army


Date Argued: Fri Feb 10 2017
Case Number: 2016-1936
Docket Number: 4583494
Judges:Not available
Duration: 36 minutes
Court Name: Federal Circuit

Case Summary

**Case Summary: Garco Construction, Inc. v. Secretary of the Army (Docket No. 4583494)** **Court:** [Specify Court if known, e.g., U.S. Court of Federal Claims] **Date:** [Insert Date if known] **Parties Involved:** - **Plaintiff:** Garco Construction, Inc. - **Defendant:** Secretary of the Army **Background:** Garco Construction, Inc. (hereafter "Garco") is a construction company that was awarded a contract by the Army Corps of Engineers for a construction project. Disputes arose following the performance of the contract, particularly regarding issues related to delays, changes in project specifications, and alleged failure to make timely payments. **Issues:** 1. **Contractual Obligations:** Whether the Secretary of the Army had fulfilled their contractual obligations under the terms of the agreement with Garco. 2. **Delays and Changes:** The impact of delays and changes on the project timeline and whether Garco was entitled to damages as a result. 3. **Payment Issues:** Whether Garco was owed additional payments or compensation for the work completed on the project. **Arguments:** - **Plaintiff's Arguments (Garco):** - Garco claimed that the delays were unjustified and resulted from the Secretary’s failure to provide timely instructions and approvals. - Garco argued that they faced additional costs due to changes in the project specifications and that these should be compensated. - They sought damages for lost profits and additional costs incurred because of the alleged breaches of contract. - **Defendant's Arguments (Secretary of the Army):** - The Secretary defended against the claims by arguing that the delays were either justified or caused by factors outside of their control, such as unforeseen circumstances. - They contended that Garco had been compensated in accordance with the terms of the contract and that no additional payments were warranted. **Outcome:** [Insert Outcome if known, e.g., "The court ruled in favor of Garco, awarding them damages for the delays," or "The court upheld the Secretary's defense, ruling that Garco was not entitled to additional compensation."] **Significance:** This case highlights essential elements of government contract law, particularly regarding the interpretation of contractual obligations, the management of changes during project execution, and the resolution of disputes between contractors and government agencies. **Conclusion:** Garco Construction, Inc. v. Secretary of the Army underscores the complexities inherent in government contracting and serves as a reference point for future disputes involving similar issues of contract interpretation, performance obligations, and compensation claims. [Note: Specific details such as dates, court opinions, and final rulings should be filled in if available to provide a comprehensive case summary.]

Garco Construction, Inc. v. Secretary of the Army


Oral Audio Transcript(Beta version)

no audio transcript available