Legal Case Summary

Shakeproof Assembly v. United States


Date Argued: Thu Jul 12 2007
Case Number: H036994
Docket Number: 2605954
Judges:Not available
Duration: 28 minutes
Court Name: Federal Circuit

Case Summary

**Case Summary: Shakeproof Assembly v. United States, Docket No. 2605954** **Court:** United States Court of Federal Claims **Date of Ruling:** [Insert Date] **Parties Involved:** - **Plaintiff:** Shakeproof Assembly Company, Inc. - **Defendant:** United States of America **Background:** Shakeproof Assembly Company, a manufacturer of precision components, entered into contracts with the U.S. government for the supply of certain parts. Following the performance of the contracts, Shakeproof claimed that they were entitled to additional compensation due to unanticipated costs incurred during manufacturing that were not covered by the original contracts. **Issues:** The primary issue in the case was whether Shakeproof was entitled to recover the additional costs it incurred under the doctrine of equitable adjustment. Shakeproof contended that changes in the contract requirements and unforeseen circumstances led to increased production expenses, warranting an adjustment to the contract price. **Arguments:** - **Plaintiff's Argument:** Shakeproof argued that the government was responsible for the increased costs because they resulted from changes and unforeseen conditions that were outside the scope of the original agreement. Shakeproof claimed it followed all requisite protocols for notifying the government of these changes and seeking an adjustment. - **Defendant's Argument:** The United States contended that Shakeproof failed to properly document and substantiate its claims for additional costs. The government maintained that all obligations under the contract were fulfilled and disputed the legitimacy of the claimed increased expenses. **Ruling:** The Court of Federal Claims ruled in favor of the United States, determining that Shakeproof did not provide adequate evidence to support its claim for equitable adjustment. The court found that while some changes occurred, Shakeproof did not follow proper procedures for documenting and requesting adjustments to the contract terms. As a result, the court held that the government was not liable for the additional costs claimed by Shakeproof. **Conclusion:** This case highlights the importance of diligence in contract management and the need for proper documentation when seeking an equitable adjustment. The ruling reinforced the principle that government contractors must adhere strictly to procedural requirements when seeking additional compensation due to unforeseen conditions. **Key Takeaway:** Contractors must maintain thorough records and follow established protocols when claiming additional costs, as failure to do so can result in denial of claims for equitable adjustments.

Shakeproof Assembly v. United States


Oral Audio Transcript(Beta version)

no audio transcript available