Legal Case Summary

Steve Spiess Construction, Inc. v. L.J. Keefe, Co.


Date Argued: Wed Sep 09 2015
Case Number: 3-14-0794
Docket Number: 3083718
Judges:Not available
Duration: 35 minutes
Court Name: Appellate Court of Illinois

Case Summary

**Case Summary: Steve Spiess Construction, Inc. v. L.J. Keefe Co.** **Docket Number:** 3083718 **Court:** [Specify Court, if known] **Date:** [Specify date of decision, if known] **Background:** Steve Spiess Construction, Inc. (Plaintiff) filed a lawsuit against L.J. Keefe Co. (Defendant) regarding a contractual dispute arising from a construction project. The Plaintiff claimed that the Defendant failed to uphold its obligations under a construction contract, resulting in financial losses and delays in project completion. **Facts:** - Steve Spiess Construction, Inc. was engaged by L.J. Keefe Co. to carry out specified construction work. - The Plaintiff alleged that the Defendant breached the contract by not providing necessary materials on time and failing to comply with project specifications. - The Plaintiff sought damages for delays and additional costs incurred due to the Defendant's alleged breach. **Issues:** 1. Did L.J. Keefe Co. breach the contract with Steve Spiess Construction, Inc.? 2. What damages, if any, is the Plaintiff entitled to recover as a result of the alleged breach? **Ruling:** The court found in favor of Steve Spiess Construction, Inc., ruling that L.J. Keefe Co. did indeed breach their contractual obligations. The court held that the delay in providing materials and failure to meet the agreed-upon specifications constituted a significant breach that adversely affected the construction timeline and incurred additional costs for the Plaintiff. **Damages:** The court awarded Steve Spiess Construction, Inc. monetary damages to cover the financial losses sustained due to the delays and additional expenses directly linked to the breach of contract by L.J. Keefe Co. **Conclusion:** This case emphasizes the importance of adhering to contractual obligations in construction agreements. It also highlights the potential financial repercussions for parties that fail to fulfill their contractual duties, as seen in the damages awarded to Steve Spiess Construction, Inc. in this matter. **Key Takeaways:** - Breach of contract in construction can lead to substantial financial liabilities. - Proper contract management and adherence to deadlines are crucial for all parties involved in a construction project. *Note: This summary is a condensed version of the case and may not capture all details or nuances. Further legal analysis may be necessary for a comprehensive understanding of the case.*

Steve Spiess Construction, Inc. v. L.J. Keefe, Co.


Oral Audio Transcript(Beta version)

no audio transcript available