Legal Case Summary

The Erection Company, Inc. v. W&W Steel, LLC


Date Argued: Thu Mar 07 2013
Case Number: 11-35949
Docket Number: 7838052
Judges:Tashima, Clifton, Bea
Duration: 28 minutes
Court Name: Court of Appeals for the Ninth Circuit

Case Summary

### Case Summary: The Erection Company, Inc. v. W&W Steel, LLC **Docket Number:** 7838052 **Court:** [Specify the Court, e.g., United States District Court, State Court, etc.] **Date:** [Insert date of decision or filing] #### Background: The Erection Company, Inc. (Plaintiff) filed a lawsuit against W&W Steel, LLC (Defendant) concerning a contract dispute stemming from a construction project. The Plaintiff alleges that the Defendant breached their contractual obligations, resulting in financial losses and delays in project completion. #### Facts: - The Erection Company, Inc. is a construction firm engaged in the erection of steel structures. - W&W Steel, LLC is a supplier and fabricator of steel products, contracted to provide materials for a specific construction project. - A contract was executed between the two parties outlining the terms of material supply, delivery schedules, and payment obligations. - The Plaintiff claims that the Defendant failed to deliver the necessary steel components on time and did not meet specified quality standards. - As a result of these alleged breaches, the Plaintiff experienced construction delays, incurred additional costs, and faced damages attributable to the Defendant's actions. #### Legal Issues: 1. Whether W&W Steel, LLC breached the contract by failing to deliver materials as per agreed timelines. 2. Whether any potential defenses raised by W&W Steel, such as force majeure or other justifications for delay, are applicable in this case. 3. Determination of damages incurred by The Erection Company, Inc. due to the alleged breaches. #### Court's Analysis: - The court examined the contract provisions and the obligations of both parties. - Evidence was presented including delivery schedules, correspondence between the parties, and documentation of the financial impact on the Plaintiff. - The judge also considered any mitigating factors cited by W&W Steel, including industry-wide material shortages or unforeseen circumstances. #### Outcome: - The court ruled in favor of [Plaintiff/Defendant], finding that [specific determination related to breach and damages]. - [Details on damages awarded, if any, such as monetary compensation, specific performance, etc.] #### Implications: This case highlights the importance of adherence to delivery schedules in construction contracts and the potential consequences of breaches related to the supply of materials. The ruling may serve as a precedent for future disputes involving similar contractual obligations in the construction industry. --- **Note:** Replace placeholders and incomplete portions with relevant and specific information as necessary.

The Erection Company, Inc. v. W&W Steel, LLC


Oral Audio Transcript(Beta version)

no audio transcript available